Before power ON:
Double check all the power cables and communication cables.
•
Turn on the 1st BMS (Battery Control Modules) of battery string.
•
The second BMS must be turned on after the first battery string's self-check is
•
successful.
Then turn on the battery strings on one by one from 1st BMS to the last BMS .
•
MBMS must be turned on after all battery strings self-check finish.
•
Page 22