Power-On Of Blade Server - NEC Express5800/B120e User Manual

Hide thumbs Also See for Express5800/B120e:
Table of Contents

Advertisement

Chapter 3 Setup
1.

Power-on of Blade Server

There are the following three ways to turn on the power of the CPU blade. Turn on the power of the CPU blade
in any of the three ways after turning on the powers of the display unit and peripherals connected to the CPU
blade.
82
Important
Perform the power-on operation of the CPU blade by either the use of the POWER
switch or the remote power-on after the period of 60 seconds or longer has passed
from the supply of AC power to every power unit (POWER lamp on CPU blade is lit
amber). The power-on operation within the period of 60 seconds from the supply of
AC power to every power unit may not turn on the power of the CPU blade. If so,
turn on the power of the CPU blade by using the POWER switch after making sure
that the AC power is supplied to every power unit.
Note
If a power cord on the Blade Enclosure is connected to a power controller including an
uninterruptible power supply (UPS), make sure that the power of the power controller is
turned on.
Tips
When the power is supplied to the CPU blade, the initial diagnosis is executed for about
60 seconds. In this period, the POWER switch is disabled. Power on the CPU blade about
60 seconds immediately after you installed the CPU blade or turned on the power.
Express5800/B120e User's Guide
1. Power-on of Blade Server

Advertisement

Table of Contents
loading

Table of Contents