1.3.

External Storage (JBOD)

In case you have a 2TB appliance with an external storage please connect the storage to
nd
the 2
RAID controller.
The RAID controller is mounted in PCI slot 5. Please connect its port "A" to port "0" of the
JBOD.
Please connect two power cables to the external storage as well.

2. Start the Server

2.1.

Power on the server

Pressing the SYSTEM POWER Switch at the front of the server turns on the server.
Turn on the server by using the following procedure.
Important
• Do not power on the server before amber SYSTEM POWER LED is unlit.
• Wait for at least 30 seconds before pressing the SYSTEM POWER switch on the
server after turning off the server.
1. Turn on the peripheral devices and display unit.
Note
If the power cord is connected to power control system such as an Uninterruptible Power
Supply (UPS), make sure that the power control system is turned on.
2. Remove Front Bezel, if mounted.
3. Press the SYSTEM POWER switch at the front of the server.
SYSTEM POWER LED is lit green and after a while, POST appears on the display.
Important
Do not connect or disconnect USB device while POST is running.