Carrying-In With Rolling Work; Procedure And Note For Horizontal Pulling Installation; Installation Location; Installation Space - Carrier 16LJ-F Series Installation Manual

Absorption chiller
Hide thumbs Also See for 16LJ-F Series:
Table of Contents

Advertisement

2-3. Carrying-in with rolling work

Size of the equipment hatch and the carrying-in entrance shall exceed the overall dimension which is
indicated on the specification. If the unit is rolled on logs, size of the rolls and soleplate shall be
considered.
Wire
The rolls and soleplate shall be set underneath the base of the main body as shown by the diagram.
Note
*The above procedures shall also be applied to the multi section shipping unit.
*Unit appearance at the installation varies by model.

2-4. Procedure and note for horizontal pulling installation

The pulling wire should be connected to the base of the main unit as shown by the diagram. Pull the
unit gently. If the ground or floor is inclined the unit shall be pulled ahead and behind.

2-5. Installation location

(1) Set the chiller on a firm and flat floor.
(2) The installation location should be free from corrosive gas, dust and high-humidity.

2-6. Installation space

Ensure the space based on the external dimensions in the contract specification.
(1) Tube removal space
To enable the replacement of the all heat transfer tubes, the space must be secured at either end in a
longitudinal direction of the chiller. Refer to the detail data on the "Dimensions" in the specification.
Temporary transfer of the obstacles is a choice to make the space at the case may be.
(2) Maintenance space
At lease 0.5m (2feet)-wide maintenance space is required around the unit. Also the maintenance
space for the facility equipment such as valves and instruments should be considered.
(3) Upper clearance of the unit
At least 0.4m (16 inch) is required.
Main body base
4

Advertisement

Table of Contents
loading

Table of Contents