Guttering + Downpipe
•
Join lengths of gutter TR22, to match the length
of the shed by notching the roller edge of one to
allow the other to slide into it.
•
Put silicone in the joint and then use rivets,
FAST009, to fasten the sections together.
•
Repeat this for the other side.
•
Mark the rectangular cutout to suit the downpipe
drop RWG18 at the end you select.
•
Remove material and fix RWG18 with silicone and
rivets.
•
Mark a line 110mm down from the top of the outer
purlins at either end of the shed. Run a stringline
between these marks. This is a reference to align
the bottom position of the gutter brackets, RWG06.
•
RWG06 are to be fixed to the sheeting rib at either
end and spaced equally along the shed length.
•
You may wish to allow for a slight fall to the
downpipe position.
•
Fix gutter onto brackets equally at both ends, push
top of bracket into outer roll of gutter and bend
small support arm down to hold the inner face.
•
Rivet the brackets to the gutter through the bottom
of each bracket.
•
Fit downpipes to drops with silicone and rivets.
Secure to wall sheeting with downpipe strap bent
to suit.
Barge Capping and Trim
•
Fit barge capping (TR06) to the front and rear
gables, fixing where there is a purlin beneath it.
•
Fit TR21 between sheet and frame directly above
roller door. Two lengths will be required.
•
Measure and cut TR19 to suit either side of roller
door opening, covering the raw edge of 237-1.
Roller Door Installation
•
These instructions and components are located
with the roller door.
• FAST081 are to be used to fix roller door
guides.
Absco Industries
Assembly Instruction Manual
ABSCO GARAGE
MODEL: RG37601N2
3.7m W x 6.0m D x 3.2m H
Model: RG37601N2
TR25
RWG06
TR21
31/08/20
RWG18
TR22
Cutout for downpipe
drop at back edge of
gutter.
Bend down the two arms
of the bracket over the
back edge of the gutter.
TR22
TR06
TR19
23