7.1.4 Installation of piping insulation
With the exception of joint insulation, insulation should be applied to piping before fixing the piping in place. Insulation at
joints in refrigerant piping should be applied after the gastightness test has been completed.
Notes for installers
 Installation of insulation should be carried out in a manner suited to the type of insulation material being used.
 Ensure there are no gaps at the joints between sections of insulation.
 Do not apply tape too tightly as doing so may shrink insulation, reducing its insulating properties leading to
condensation and loss of efficiency.
 Insulate gas and liquid pipes separately, otherwise heat exchange between the two sides will greatly impact
efficiency.
 Do not bind the separately insulated gas and liquid pipes together too tightly as doing so can damage the joints
between sections of insulation.
7.1.5 Installation of joint insulation
Insulation at joints in the refrigerant piping should be installed after the gastightness test has been successfully completed.
The procedure at each joint is as follows:
1. Cut a section of insulation 50 to 100mm longer than the gap to be filled. Ensure that the cross-sectional and longitudinal
openings are all cut evenly.
2. Embed the section into the gap ensuring that the ends abut tightly to the sections of insulation either side of the gap.
3. Glue the longitudinal cut and the joints with the sections of insulation either side of the gap.
4. Seal the seams with tape.
7.2 Drain Piping Insulation
 Use rubber/plastic insulating tube with a B1 fire resistance rating.
 The insulation should typically be in excess of 10mm thick.
 For drain piping installed inside a wall, insulation is not required.
 Use suitable adhesive to seal seams and joints in the insulation and then bind with cloth reinforced tape of width not
less than 50mm. Ensure tape is fixed firmly to avoid condensation.
 Ensure the drain piping insulation adjacent to the indoor unit drainage water outlet is fixed to the unit itself using
adhesive, to prevent condensation and dripping.
7.3 Ducting Insulation
 Suitable insulation should be added to ducting in according with all applicable legislation.
Figure 3-7.1: Installation of joint insulation (unit: mm)
Insulation
material
straight-through joint
300
Copper pipe
Insulation
material
400
V6R VRF 50/60Hz
167