Initial Power Activation Setting - Hitachi PSC-A32MN Operation Manual

Hide thumbs Also See for PSC-A32MN:
Table of Contents

Advertisement

6. Initial Power Activation Setting

< Preparation 1 >
Turn on the power supply of the air conditioners.
To protect the compressor, the power supply should be turned on 12 hours before the operation is started.
Do not turn off the power supply during the air conditioning seasons.
< Preparation 2 >
After the preparation 1 is completed, turn on the power supply of the central station.
"Start-up" will be displayed for a while and the screen changes to "Monitor (All Groups)".
NOTE:
Setting the date and time may be required after long-term power failure.
In that case, "Set Date/Time" will be displayed on the screen. If "Set" is tapped, "Date and time settings"
will be displayed.
Refer to the item 8.6 for setting the date and time.
P5415644
7

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents