Mounting the transducer

When all the preparations have been made, the transducer is mounted. If required, additional
and more detailed procedures must be provided by the installation ship yard.
Prerequisites
The following requirements must be
met before mounting the transducer:
• The physical location of the
transducer has been determined.
• The mounting ring has been
installed.
• The steel conduit is mounted with
all installation work finalized.
Note
Whenever relevant, all drawings
as well as the physical installation
of each device must be approved
by the vessel's national registry and
corresponding maritime authority
and/or classification society.
The following special tools are
required for this installation:
• Torque wrench for the mounting
bolts
• Loctite 270 (permanent high-strength threadlocker)
• Lifting device
Illustration:
Mounting ring
A
Clamping ring
B
Cable service loop
C
Bolt
D
404292/D