Alpha ESS eSTORE-BAT-10.3 Manual page 17

Battery module
Table of Contents

Advertisement

Your Smart Energy
Installation
Step5. Remove the inverter and accessories.
Step6. Placed the cable box bracket on the battery and position it with 2 x M5*10
positioning screws.
Step7. Please drill four holes (two on each side) directly on the wall at the marking positions
of the bracket with an impact drill (bit φ 8.0 mm, length 60 cm) and the depth of each hole
should be about 7 cm. Fixed cable box bracket on the wall with 4 x M8*60 and 4 x M6
gaskets.
Step8. Remove the positioning screws.
Step9. Fixed the cable box on cable box bracket and lock the cable box with screws.
______________________________________________________________________
Alpha ESS Co., Ltd.
Page 15 of 31