Huawei FusionDC1000A Installation Manual page 60

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Installation Guide (IT Scenario)
Figure 5-5 Adjusting the awning
(A) Holeless washer
Step 5 Secure the awning.
Step 6 Apply white sealant on the joint between the awning top and the pre-fab. module.
Issue 01 (2021-04-20)
Copyright © Huawei Technologies Co., Ltd.
5 Installing External Accessories for the Pre-fab.
(B) Round-hole washer
Module
53

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents