11.Removal of Swing Motors

Procedure
Step
1. Remove the swing motors
for horizontal blades.
1
Cut the clamp.
2
Release the lead wire
for the swing motors
from the 3 hooks.
Remove the 2 screws
3
and remove the swing
motor for the lower
blade (small).
4
Remove the screw and
remove the swing
motor for the upper
blade (large).
2. Remove the swing motor
for vertical blades.
Remove the screw of
1
the drain hose.
Remove the 2 screws
2
of the swing motor
assembly.
Removal Procedure
Warning Be sure to wait for 10 minutes or more after turning off all power
supplies before disassembling work.
Procedure
Hook
For upper blade
Swing motor assembly
Removal of Swing Motors
Preparation
Remove the electrical box
according to "Removal of
Electrical Box".
Caution
When reassembling, do not
confuse the installing order
of the 2 motors and the
(R13969)
colors of the connectors.
If you set the connectors or
For lower blade
motors opposite, the
horizontal blades do not
move smoothly or the noise
may be heard.
(1) Set the motor for the upper
blade first.
(connector: green)
(2) Then, set the motor for the
lower blade.
(connector: red)
(R13970)
(R5733)