2.2.2. Maintenance Space Requirements

When installing, ensure to reserve a maintenance space of at least 600 mm in the front, rear, and bottom sides of the unit, as
shown in
Figure
2-2.
Table 2-1
represents the minimum maintenance space requirements of the unit.
Note 1: The side with the operation indicator light is defined as the front of the unit, and the other side is defined as the
rear of the unit. These spaces are used for regular maintenance, such as replacing filters, fans, electronic expansion
valves, and maintaining electronic control boxes.
Note 2: In case of a special application, consult Vertiv local representative.

2.3. Unpacking and Inspection

2.3.1. Transportation and Handling

1. When transporting, the priority shall be given to rail or water transportation. If user choose road transportation then a
road with better road conditions should be select to prevent excessive bumps.
2. Vertiv™ Liebert® XDO unit is heavy. Refer
forklifts are required for unloading and handling.
3. When transporting, transport the unit to the place closest to the installation site.
the unit and the fork should be at the center of gravity to prevent tipping of the unit.
7
Figure 2-2 Maintenance Space of the Unit
Table 2-1 Minimum Maintenance Space (unit: mm)
Location
XDO020CS15HC
Front
600 mm
Rear
600 mm
Top
600 mm
Table 2-3
for weight parameters; mechanical handling tools, such as electric
Figure 2-3
illustrates the forklift lifting
Mechanical Installation