12. Remove and replace seals and wipers.
13. Assemble piston and gland to piston ram.
14. Assemble ram nut to piston ram and torque
to 100 ft/lb.
15. Lubricate piston and seals and install cylinder.
16. Insert retainer ring.
17. Install cylinder and hydraulic lines.
18. Fill reservoir.
19. Cycle lift up and down a few inches, remove
FIGURE 4: XZ Pinch Points, UP
Page 16 —
PRESTO OWNER'S MANUAL: XZ, XZT FLOOR LEVEL LIFTS & TZ FLOOR LEVEL TILTS
chocks, cycle lift 2-3 times and recheck oil reservoir
for oil level.
C. REPLACING LEG ROLLERS ON XZ LIFT:
1. Raise the lift. Chock lift with safety chocks pro-
vided and secure per Section 5B.
2. Disconnect the electrical power.
3. Replace one roller at a time by removing retainer
clips, shields and roller. Clean and do not lubricate
axle. Replace with new rollers, shields and clips.
4. Raise lift and remove chocks. Cycle lift 2-3 times
and check shields and clips prior to returning to ser-
vice.