Step
Bring the Upper Ring close to the Lower Ring for alignment checks. Verify
8.1.8
alignment before any force is applied to compress the Lightband.
Per Figure 8-4 ensure:
1. Cutout in Upper Ring aligns over Motor Bracket Assembly on Lower Ring.
2. All Separation Connector/Switch cutouts align.
3. All Separation Spring tips protrude through appropriate holes in the Upper
Ring.
Note if using a crane to lower a payload, perform all crane adjustments with
the Upper Ring above the Separation Springs to prevent damage due to
excess crane movement.
For horizontal integration, see Section 13.
PSC Proprietary
Procedure
Figure 8-4: Aligning the Lower and Upper Rings.
2000781J MkII MLB Operating Procedure
Date & Initials
Tech.
QA
Page 20 of 50