In contrast to the slave APUs, the number of strings is retrieved first for
the master. The number of strings corresponds to the number of storage
systems in the master/slave configuration (e.g. master + slave 1 = 2
strings). Confirm the correct number by tapping next to the display
twice. In the event of discrepancies, check the CAN OUT > CAN IN
cabling, the termination and the addressing. If the error persists, contact
the service center.
The number of recognized battery modules (14 or 16) will be displayed
on the screen of the master SMA HV APU. Confirm the correct number
by tapping twice. In the event of discrepancies, take the
STORAGE-67-TS-10 out of operation and check the BAT COM cabling.
If the error persists, contact the service center.
Tap next to the display once more time to call up the next menu item.
you will now see the assigned IP address. It must start with 192.168.4. ...
The STORAGE-67-TS-10 will switch to "INIT" mode and the on-off
"SWITCH"
will start flashing.
 17
Start the commissioning process of the STPS 60-10 with the LCS tool.
The software and instructions are located on the USB drive
the commissioning process has been successfully completed, all
STORAGE-67-TS-10s will change to the "PRECHG" pre-charge mode.
After successful completion of the pre-charge, the on-off "SWITCH"
on all SMA HV APUs in the master/slave configuration will remain
 17
permanently lit. The status "Ok" will be shown on the display of the
SMA HV APU. Now all STORAGE-67-TS-10s are now ready for oper-
ation.