Test run

 Before test run
• Before turning on the circuit breaker, carry out the
following procedure.
1) By using insulation tester (500 VMΩ), check that
resistance of 1 MΩ or more exists between the
terminal block L to N and the earth (grounding).
If resistance of less than 1 MΩ is detected, do
not run the unit.
2) Check the valve of the outdoor unit that is fully
open.
• To protect the compressor at start-up, turn on the
power supply 12 hours or more before operation.
• Before starting the test run, follow the Installation
Manual included with the outdoor unit to set the
address.
• The water supply to the water piping system (above
10°C) should be completed and the pump should be
wired prior to the test run.
When water is not supplied to hot water module, and
when the water does not circulate, the entire system
will stop with an error detected (check code: A01).
 Perform test run
Use the wired remote controller to operate the unit as
usual.
For procedures of this operation, refer to the Owner's
Manual.
A forced test run can be executed in the following
procedure even if the operation stops by thermostat-
OFF. In order to prevent a serial operation, the forced
test run is released after 60 minutes have passed and
returns to the usual operation.
WARNING
Do not use the forced test run for modes other than test
run, as this will put excessive loads on the device.
65-EN
Wired remote controller
Be sure to stop the air conditioner (including the
Hot water module) before making settings.
(Change the setup while the air conditioner is not working.)
4
3
3
1
2
1
Push and hold OFF timer button and [
setting button simultaneously for 10
seconds or more. [TEST] is displayed on the
display part and the test run is permitted.
2
Push ON/OFF button.
3
Push the menu button to heating mode
• The temperature setting function does not work
during test run.
• The check code is displayed as usual.
4
After the test run, push OFF timer button to
stop a test run.
([TEST] disappears on the display and the air
conditioner enters the normal stop mode.)
– 33 –
 Items to check before conducting a test run
Check the following items before the test run. The numbers in (parentheses) are the chapter numbers in the table
of contents of the installation manual.
Installation work
Piping work
]
Electric wiring work
.
Outdoor unit board settings
*1 Do not operate the air conditioner (run the compressor) before the address to the hot water module is fixed.
Doing so will cause the heat exchanger in the hot water module to freeze, rupture, and leak water.
*2 Set DIP switch 4 of SW09 or SW103 on the P.C. board of the header outdoor unit to "ON" (factory default is
"OFF").
The VRF system will be stopped to avoid water freezing when the power supply is disconnected.
NOTE
Before you run the compressor, always confirm that the hot water module is operable (power on, address fixed,
communication wiring complete).
Failure to do this will cause the heat exchanger in the hot water module to freeze, rupture, and leak water.
Is the equipment attached to the legs with bolts? (See chapter 5.)
Is there sufficient open space around the equipment for servicing? (See
chapter 4.)
Have the criteria for selecting a location to install the equipment been met?
(See chapter 4.)
Are all of the pipes connected correctly? (See chapter 6 to 8.)
Are there no water leaks?
Is the flow rate suitable? (See chapter 6.)
Is the strainer in a suitable location? (See chapters 3 and 6.)
Is the line heater in a suitable location and is the flow rate suitable? (See
chapters 3 and 6.)
Have suitable safety devices for pressure relief and expansion tanks been
installed? (See chapters 3 and 6.)
Is the shut-off valve in a suitable location? (See chapters 3 and 6.)
Is the air vent valve in a suitable location? (See chapters 3 and 6.)
Is the piping material suitably heat resistant and corrosion resistant? (See
chapters 6 to 8.)
Can water discharge through the drain? (See chapter 7.)
Was the heat-retention work done suitably? (See chapters 6 to 8.)
Is the electric wiring connected correctly? (See chapter 9.)
Is the electric wiring thick enough? (See chapter 9.)
Is the power fed from a dedicated ground fault circuit breaker?
Is the output terminal wired? (See chapter 9.)
Is the addressed fixed? (*1)
Has DIP switch 4 of SW09 or SW103 on the interface board of the header
outdoor unit been set to "ON" (factory default is "OFF")? (See chapter 9.)
(*2)
Check
66-EN