4.11 Final installation checks

After unit installation and connection is complete, there are a few important final steps to perform:
Clean the equipment carefully to remove any debris, wire strands, packing material, etc., which may have
accumulated.
Replace any barriers which may have been removed during installation.
Ensure kickplates are installed, if they were removed during installation.
Inspect side panels for damage.
Inspect all connectors for proper electrical and physical integrity.
Ensure proper cabinet grounding; verify external ground wire has been brought into the cabinet and
connected to the ground bus bar only.
Verify all power wire connections are crimped or tightened properly. Recommended torque values are
listed in the Appendix section of this document.
Verify all breakers are in the open position.
ABB Service Center personnel can provide a more detailed final checklist prior to energizing the unit.
®