Checklist During Commissioning; About The Test Run; To Perform A Test Run (7-Leds Display); To Perform A Test Run (7-Segment Display) - Daikin VRV IV RKXYQ5T8Y1B Series Installation And Operation Manual

Compressor unit for indoor installation
Hide thumbs Also See for VRV IV RKXYQ5T8Y1B Series:
Table of Contents

Advertisement

Refrigerant leak
Check the inside of the unit on refrigerant leakage. If there
is a refrigerant leak, try to repair the leak. If the repair is
unsuccessful, call your local dealer. Do not touch any
refrigerant which has leaked out from refrigerant piping
connections. This may result in frostbite.
Oil leak
Check the compressor for oil leakage. If there is an oil
leak, try to repair the leak. If the repairing is unsuccessful,
call your local dealer.
Air inlet/outlet
Check that the air inlet and outlet of the unit is NOT
obstructed by paper sheets, cardboard, or any other
material.
Additional refrigerant charge
The amount of refrigerant to be added to the unit shall be
written on the included "Added refrigerant" plate and
attached to the rear side of the front cover.
Installation date and field setting
Be sure to keep a record of the installation date on the
sticker on the rear of the front panel according to
EN60335‑2‑40 and keep record of the contents of the field
setting(s).
Insulation and air leaks
Make sure the unit is fully insulated and checked for air
leaks.
Possible consequence: Condensate water might drip.
Drainage
Make sure drainage flows smoothly.
Possible consequence: Condensate water might drip.
External static pressure
Make sure the external static pressure is set.
Possible consequence: Insufficient cooling or heating.
17.3

Checklist during commissioning

To perform a test run.
17.3.1

About the test run

NOTICE
Make sure to carry out the test run after the first
installation. Otherwise, the malfunction code
displayed on the user interface and normal operation or
individual indoor unit test run cannot be carried out.
The procedure below describes the test operation of the complete
system. This operation checks and judges following items:
▪ Check of wrong wiring (communication check with indoor units
and heat exchanger unit).
▪ Check of the stop valves opening.
▪ Check of wrong piping. Example: Gas or liquid pipes switched.
▪ Judgement of piping length.
Abnormalities on indoor units cannot be checked for each unit
separately. After the test operation is finished, check the indoor units
one by one by performing a normal operation using the user
interface. Refer to the indoor unit installation manual for more details
concerning the individual test run.
RKXYQ5T8 + RKXYQ8T7Y1B
VRV IV compressor unit for indoor installation
4P499900-1A – 2020.10
INFORMATION
▪ It may take 10 minutes to achieve a uniform refrigerant
state before the compressor starts.
▪ During the test operation, the refrigerant running sound
or the magnetic sound of a solenoid valve may become
loud and the display indication may change. These are
not malfunctions.
17.3.2

To perform a test run (7-LEDs display)

(in case of 5 HP)
1 Make sure all field settings you want are set; see
settings" [ 4  29].
field
2 Turn ON the power to the compressor unit, heat exchanger unit,
and the connected indoor units.
NOTICE
Be sure to turn ON the power 6 hours before operation in
order to have power running to the crankcase heater and
to protect the compressor.
3 Make sure the default (idle) situation is existing (H1P is OFF);
see
"To access mode 1 or
more. The unit will start test operation.
Result: The test operation is automatically carried out, the
compressor unit H2P flashes and the indication "Test operation"
and "Under centralised control" will display on the user interface
of indoor units.
Steps during the automatic system test run procedure:
Step
INFORMATION
During the test operation, it is not possible to stop the unit
operation from a user interface. To abort the operation,
press BS3. The unit will stop after ±30 seconds.
4 Check the test operation results on the compressor unit 7‑LEDs
display.
will be
Completion
Normal
completion
Abnormal
completion
17.3.3

To perform a test run (7-segment display)

(in case of 8 HP)
1 Make sure all field settings you want are set; see
settings" [ 4  29].
field
2 Turn ON the power to the compressor unit, heat exchanger unit,
and the connected indoor units.
17 Commissioning
2" [ 4  30]. Push BS4 for 5 seconds or
Description
Control before start up (pressure
equalisation)
Cooling start up control
Cooling stable condition
Communication check
Stop valve check
Pipe length check
Pump down operation
Unit stop
Description
Refer to
"Correcting after abnormal completion
run" [ 4  38] to take actions for
of the test
correcting the abnormality. When the test
operation is fully completed, normal operation
will be possible after 5 minutes.
Installation and operation manual
"16.1 Making
"16.1 Making
37