Eaton Cutler-Hammer CHGENLC100ATS1SE O & M Manual page 41

Automatic transfer switch with atc-100 control

Advertisement

O & M Manual for the CHGENLC Automatic
Transfer Switch with ATC-100 Control
8.3 Optional SurgeCable
Figure 73. SurgeCable Installed on the TVSS.
Note: The Eaton SurgeCable is designed to mount directly to the TVSS
when it is externally mounted to the ATS enclosure. If the TVSS was fac-
tory installed inside the 100 A or 200 A SE ATS enclosure, the SurgeCable
MUST BE mounted outside the ATS and wired into the ATS. See Section
7.4.1.13 for installation/replacement information and the Instruction Bulle-
tin supplied with the SurgeCable for additional information.
Note: If the SurgeCable will be mounted to the TVSS, no ground wire is
required between the SurgeCable and ATS. The TVSS ground will also
ground the SurgeCable.
Step 1: Align the quick connector with the receptacle on the right
side, left side, or bottom of the TVSS. Slide the Surge-
Cable into the receptacle until completely seated (see Fig-
ure 74).
Note: The SurgeCable can also be mounted to other Eaton surge protection
devices that incorporate the quick connect feature.
Figure 74. SurgeCable Mounted to the TVSS.
Step 2: Reroute the coaxial cables to the SurgeCable.
Step 3: Connect the coaxial cables to the applicable "In" and
"Out" terminals on the SurgeCable.
Note: See the Instruction Bulletin supplied with the SurgeCable for addi-
tional connection information.
Step 4: After ensuring that all connections are tight, turn on the
protected equipment and check for proper functioning.
IB00405002E
8.4 Optional Load Shed (100 A and 200 A ATS)
If you have ordered a standard ATS and an optional load shed, or
have decided to add an optional load shed to a previously installed
ATS, follow the steps outlined below to install the option.
Figure 75. Load Shed Installed in a Standard ATS.
Step 1: Turn the utility (Source 1) power off and turn the genera-
Step 2: Align the load shed with the existing holes near the top of
Figure 76. Load Shed Installed on the Base Plate.
For more information visit: www.eaton.com
Instructional Booklet
Effective: August 2007
tor (Source 2) control selector switch to the "OFF" posi-
tion before attempting to install the load shed.
the base plate, directly above the contactor, for standard
ATSs, and directly below the neutral for SE ATSs.
Secure the load shed to the base plate using the hard-
ware supplied.
Page 41