Chapter 2. Installing Pipe Nozzles
2.3
Selecting and Marking the First Nozzle Location (cont.)
3. At the 3 o'clock position, center punch the pipe to mark the position for the center of the first nozzle.
Side View
4. Spray this area with a marking dye product. Using a metal edge, scribe a vertical and a horizontal line (6 in. long)
that intersect at the center punch mark.
Side View
6
Model T9 Ultrasonic Flow Transducer Installation Guide