Chapter 2. Installing Pipe Nozzles
2.1 Introduction
Before the T9 transducers can be installed into the pipe, you will need to install pipe nozzles. Nozzles can be installed
on a hot or cold pipe using a GE Nozzle Installation Kit. Nozzles are installed in a Tilted 45
IMPORTANT:
This procedure only applies if you are using a Nozzle Installation Kit. If you are tapping the pipe without
using a Nozzle Installation Kit, refer to the supplied drawings in your shipment. This procedure is written
and illustrated for installations on horizontal pipes; however, the procedure is the same for vertical pipe
installations.
This procedure contains the following instructions:
•
Identifying and Checking the Nozzle Installation Kit Components
•
Selecting and Marking the First Nozzle Location
•
Determining and Marking the Second Nozzle Location
•
Installing the First Welding Boss
•
Installing the First Nozzle
•
Installing the Second Welding Boss and Nozzle
•
Hot Tapping the Pipe
Model T9 Ultrasonic Flow Transducer Installation Guide
Chapter 2. Installing Pipe Nozzles
o
configuration.
3