FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 5-9 Securing a skylight
Step 2 Lift the skylight panel to the top of the aisle and use M6x16 screws to secure the skylight
panel to the skylight connective plates, as shown by (2) and (3) in
The number of M6x16 screws must be the same as the number of rivet nuts on the end
plane of the skylight connective plates.
Place the skylight based on the Keep direction label on the flat or rotating skylight.
Step 3 Install adjacent skylights in the same way.
Step 4 Keep the end planes of adjacent skylight connective plates flush with each other and connect
the adjacent skylight connective plates using two M6x16 screws with flat washers and nuts.
Issue 01 (2017-07-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Installing the Contained Aisles
Figure
5-9.
83

Advertisement

Table of Contents
loading

Table of Contents