FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 1-8 Aisle check tool
1.7 Personnel Requirements
Only trained and qualified personnel who fully understand basic safety precautions are
allowed to install and operate a modular data center.
Huawei will not be liable for any consequence caused by the violation of this document.
The requirements are as follows:
1.8 Installation Process
Figure 1-9
Issue 01 (2017-07-30)
Customers' installation personnel must be trained by Huawei and understand how to
install and operate a modular data center.
The number of installation personnel varies depending on the project progress and the
installation environment. Typically, three to five persons are required.
People who need to work at heights must have the required work permit.
shows the installation flowchart.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
1 Installation Preparations
14