Huawei FusionModule2000 Installation Manual page 130

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 7-9 300 mm wide cable trough
(1) Partition plate
Procedure
Step 1 Place two vertical plates upright on the top of the 300 mm wide cabinet, and press a tray along
the two vertical plates down to the clasps at the bottom.
Step 2 Press both sides of the V-shaped partition plate with hands to decrease the angle to a proper
degree, and clamp the clasps at the bottom into the square holes nearby.
Step 3 Align the assembled cable trough with the adjacent 600 mm wide cable troughs, and rotate the
interconnecting wrench to connect the troughs in parallel.
Figure 7-10 Connecting a 300 mm wide cable trough to a 600 mm wide cable trough
(1) Interconnecting wrench
----End
Issue 01 (2017-07-30)
(2) Vertical plate
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
7 (Optional) Installing Cable Troughs
(3) Tray