Purpose

This is the Factory Acceptance Test for the Simrad ME70 Multibeam scientific echo sounder.
The purpose of this Factory Acceptance Test is to verify that the ME70 system is fully
functional, and meets the operational requirements. It is then ready for packing and
shipment. When all the tasks have been done, the report form must be signed by the relevant
parties. The completed document then becomes the official report.
Note
In some cases the transducer is shipped to the installation shipyard before the Factory
Acceptance Test takes place. The hardware registration is then omitted. The Factory
Acceptance Test is done with a replacement transducer or a dummyload.