Complete The Installation - Kohler K-7223 Installation Manual

Bath drain
Hide thumbs Also See for K-7223:
Table of Contents

Advertisement

Available languages

Available languages

Flange
1/2"
(1.3 cm)

7. Complete the Installation

Install the drain linkage with the drain stopper and nut at least
half way down the threaded rod. The distance between the
underside of the stopper and the bath surface should be 1/2" (1.3
cm).
Adjustment
Remove the stopper from the threaded rod.
Remove the drain stopper, then loosen the nut on the threaded
rod. To raise the drain stopper, turn the nut counterclockwise. To
lower the drain stopper, turn the nut clockwise.
Reinstall the stopper onto the threaded rod.
Toggle the overflow hood handle to ensure the stopper moves up
and down at the distance of 1/2" (1.3 cm). Repeat the adjustment
procedure, if necessary.
Checkout
Make sure all connections are tight.
Close the overflow hood handle, then fill the bath with water and
check for leaks.
Check for leaks. Repair as needed.
1054248-2-B
Drain Stopper
Nut
Threaded
Rod
10
Kohler Co.

Advertisement

Table of Contents
loading

This manual is also suitable for:

7223-bn

Table of Contents