6.1 Checking Before Power-On

No.
1
2
3
4
5
6
7
8
Issue 11 (2020-08-30)
Acceptance Criteria
The SUN2000 is installed correctly and securely.
DC switches and the downstream AC switch are OFF.
All cables are connected correctly and securely.
Used cable glands are sealed and locking caps are tightened.
Unused terminals and ports are locked by watertight caps.
The installation space is proper, and the installation environment
is clean and tidy, without foreign matter.
The AC terminal cover is reinstalled.
The maintenance compartment door is closed and the door
screws are tightened.