Figure 5-5 Connecting the PE cable to the PE point (on the enclosure shell)
(1) Reserved PE point
----End
Follow-up Procedure
To enhance the corrosion resistance of a ground terminal, apply silica gel or paint
on it after connecting the PE cable.

5.4 Opening the Maintenance Compartment Door

Precautions
● Do not open the host panel cover of the SUN2000.
● Before opening the maintenance compartment door, ensure that no electrical
● If you need to open the maintenance compartment door in rainy or snowy
● Do not leave unused screws in the maintenance compartment.
Procedure
Step 1 Open the maintenance compartment door and install the support bar.
Figure 5-6 Opening the maintenance compartment door
Issue 11 (2020-08-30)
CA UTION
connections are made for the SUN2000 on the AC or DC side.
days, take protective measures to prevent rain or snow entering the
maintenance compartment. If unavoidable, do not open the maintenance
compartment door.