14 Option description

STO function activation and indication response times

Module response times only

STO activation and indication response times
STO activation response time
STO indication response time
1)
STO activation response time = delay between de-energizing the STO input and switching off the drive/
inverter output bridge
2)
STO indication response time = delay between de-energizing the STO input and indication of STO input de-
energization

Response times with typical safety relay

STO activation and indication response times
STO activation response time
STO indication response time
3)
STO activation response time = delay between de-energizing the STO relay and switching off the drive/
inverter output bridge
4)
STO indication response time = delay between de-energizing the STO relay and indication of STO input de-
energization
Typical response time
1)
2 ms
2)
1.5 ms
Typical response time
3)
52 ms
4)
51.5 ms
Maximum response time
20 ms
-
Maximum response time
70 ms
-