Installation - Alpha ESS SMILE-BAT-10.3P Installation Manual

Battery module
Hide thumbs Also See for SMILE-BAT-10.3P:
Table of Contents

Advertisement

Your Smart Energy

Installation

Where the top of the SMILE-BAT-10.3P is within 1200 mm of the ceiling or structure above
the SMILE-BAT-10.3P, the ceiling or structure surface shall be suitably non-combustible for
an area of 600 mm past the extremities of the SMILE-BAT-10.3P.
SMILE-BAT-10.3P shall be mounted with the highest point no greater than 2.2 m above the
floor or platform.
Installation
Step 1: open the battery package.
Note: The box must be placed in the direction of the label and only remove the
packaging in upwards direction. Removing the packaging in other directions is wrong.
Figure 2.1 Front side view
Figure 2.2 Left side view
______________________________________________________________________
Alpha ESS Co., Ltd.
Page 14 of 42