Verifying the Installation

No. Check Item
1
Installation of all devices in
the intelligent battery
monitoring system
2
Cable labels to the
intelligent battery
monitoring system
3
Cable connections to the
intelligent battery
monitoring system
4
CIM DIP switch
5
Positive and negative BIM
input power cables
6
Operating environment
7

System Commissioning

Set parameters on the CIM WebUI, ECC WebUI, UPS WebUI, or UPS LCD based on the scenario to
perform CIM and BIM networking. This document describes how to set parameters on the CIM WebUI.
For details about how to set parameters on other UIs, see the iBAT 2.0-CIM01C2 User Manual.
7.1
Prerequisites
Supported operating system: Windows XP or
later
Browser: Internet Explorer 9 or later, FireFox
43 or later, and Chrome 41 or later
The IP addresses, subnet masks, and
gateways for the PC and CIM are in the same
network segment.
7.2

Setting Parameters

The following describes how to set parameters for a single CIM. For details about how to set
parameters for parallel CIMs, see the iBAT 2.0-CIM01C2 User Manual.
1. Connect a straight-through cable from the PC network port to the PoE port on the smart ETH
gateway or the DATA port on the adapter.
ECC scenario
Smart ETH gateway
Acceptance Criteria
All devices in the intelligent battery monitoring
system are installed reliably.
All cables for the intelligent battery monitoring
system are connected correctly. Both ends of each
cable are labeled. Labels are clean and correct, and
provide concise and understandable description.
All cables for the intelligent battery monitoring
system are connected securely and reliably. For the
cables secured by screws, the spring washers are
flattened. All cable connections are secure. No open
circuits or hidden risks exist on cable connections.
All DIP switches on CIMs are correctly set.
Use a multimeter to check that the voltage between
the positive and negative BIM input power cables is
correct.
Conductive dust and other foreign matter are
cleaned up from the installation environment.
Adapter
12
The default settings of the IP address, subnet
mask, and gateway for the CIM are as follows:
IP address: 192.168.0.10
Subnet mask: 255.255.255.0
Gateway: 192.168.0.1
UPS scenario
Check Result
□ Passed
□ Failed
□ Passed
□ Failed
□ Passed
□ Failed
□ Passed
□ Failed
□ Passed
□ Failed
□ Passed
□ Failed