Step 7.
Slowly lower the enclosure and ensure that the other three nailheads on each side slip into the
slots.
Figure 23. ThinkAgile CP compute enclosure installation
Step 8.
To slide the ThinkAgile CP compute enclosure into the rack, first push up the rear latches on the
slide rails.
Step 9.
Push the enclosure until the slide rails click into place.
Step 10. Push up the front latches on the slide rails.
Step 11. Push the enclosure all the way into the rack.
Figure 24. Enclosure installation into rack
Step 12. Fasten the two thumbscrews located on the front of the compute enclosure.
.