5.2

5.2.1 Terminal base installation

Follow the procedure below for either IS or general-purpose module bases.
(Note that this procedure can also be carried out with the UI module fitted.)
Push the terminal base vertically downwards into the carrier ensuring the base clip clicks
into place and at the same time ensuring the upper latch is located into the mating part
on the adjacent module, if one is fitted. Use a small-bladed screwdriver to locate and
tighten the retaining screw.
Ensure that the screw is adequately tight as the contact between the terminal
base and the carrier board provides the ground path for any surge current.
Removal is the reverse of this sequence but the UI module must be removed first.
Loosen screw, press clip inwards to release and pull base vertically off carrier.
INM MTL SUM5 Rev 1
Terminals – installation and removal
Latch
Clip
Figure 5.1 - Installing a terminal base