www.ti.com
Switch, SW1
Position
7
8
3.1.2
Jumper Options
Four jumpers are associated with the digital control section; their functions are detailed in
Reference
Designator
W20
W23
J19 2-1
J19 3-4
(1)
Factory installed
3.1.3
ADS1610EVM OTR LED
When the analog input exceeds the positive full-scale value or goes below negative full-scale value of
VREF, the Out of Range (OTR) signal goes HIGH and remain high while the signal is out-of-range. When
this condition occurs, LED1 illuminates. To clear the LED, flip-flop U13 must be reset. Depending on which
position W20 is set to, the LED can be reset manually via SW2 or through programming by issuing a WR
operation from the host processor. The factory-set condition of W20 is a short across pins 2-3. This allows
the user to manually reset the LED and reset the ADS1610.
3.1.4
ADS1610 Reset
The ADS1610 can be asynchronously reset when the SYNC pin is driven low. In reset, all the digital
circuits are cleared, the data bus is LOW, and DRDY is HIGH. The ADS1610 can be reset in two ways,
using an manual reset via SW1 or by programming from the host system. If W20 pins 1-2 are shorted, the
SYNC signal must be generated by the host system. If W20 pins 2-3 are shorted, then the SYNC signal to
the ADS1610 is generated manually by momentarily depressing switch SW2.
3.1.5
Interrupt Source
Some microprocessors only recognize falling edge interrupts; others only recognize rising edge interrupts.
Some can be programmed to recognize either. W23 can be set by the user to select either rising edge or
falling edge. If a jumper is across pins 1 and 2, DRDY is applied to DRDY_OUT pin. If jumper short is
across pins 2 and 3, an inverted version of DRDY is applied to DRDY_OUT pin.
3.1.6
Base Address and Chip Select
The EVM can be mapped into a memory location by setting a base address. The EVM has four possible
base addresses. The base address is set by J19. When the logic state of the two external address signals
matches the logic state set up by the two jumpers on J19 and the access is valid memory access, the
EVM generates a CS signal for the ADC. This then can be further qualified as a read cycle or a write
(RESET) cycle. An installed jumper is equivalent to logic 0 on the corresponding address line. An
uninstalled jumper is equivalent to logic 1 on the corresponding address line.
SLAU180A – May 2006 – Revised August 2006
Submit Documentation Feedback
Table 3. Switch Function Control, SW1 (continued)
Function
Not used
Not used
Table 4. Digital Jumper
1-2
2-3
Installed
Not installed
(1)
Not installed
Installed
(1)
Installed
Not installed
Not installed
Installed
(1)
Installed
N/A
(1)
Installed
N/A
ON(LO)
Description
Set SYNCB to output of combinatory logic
Set SYNCB to user reset switch
Set DRDY_OUT to DRDY of ADS1610
Set DRDY_OUT to inverted DRDY of ADS1610.
Set U16A pin 2 to LOW. Used in EVM address decoding logic.
Set U17A pin 2 to LOW. Used in board address decoding logic.
Digital Interface
OFF(HI)
Table
4.
ADS1610EVM