6.11 NORMAL START-UP

The start-up procedure is indicated below. The flow diagram shows the
variables based on the characteristics of the machine and the water
circuit.
During start-up, it's essential that the plant water temperature
stabilizes to the set point value before activating CCUs.
NO
Is the water circuit
divided into primary
NO
and secondary
circuit?
2.
Start the circuit's
pump
3.
Wait for at least 1 min
and start the
machine.
4.
Wait until the circuit
reaches the set point
temperature
If there are several distinct areas, spread the CCU activation,
so that the machine can adjust to the increase in load step-by-step.
RC GROUP S.p.A I_TRP_0909_GB
1. Check that CCUs are OFF (fans OFF)
Is the machine
equipped
with the water
pumping
unit (optional)?
YES
2.
Start the primary
circuit's pump
3.
Wait for at least 1 min
and start the machine
4.
Wait until the primary
circuit reaches the set
point temperature, then
start the secondary
circuit's
pump
5. Wait until the
secondary
circuit reaches the set
point temperature
Turn on CCUs (fans turning on)
WARNING - CAUTION
Do not change the plant loads suddenly.
Chapter 6 - INFORMATION FOR USE
Is the water circuit
divided into primary
NO
and secondary
circuit?
2.
Start the machine
3.
Wait until the circuit
reaches the set point
temperature
YES
YES
2.
Start the machine
3.
Wait until the primary
circuit reaches the set
point temperature, then
start the secondary
circuit's pump
4.
Wait until the
secondary
circuit reaches the set
point temperature