Operation

7.3 Incremental heating test

Proceed as follows during the incremental
heating test:
1. Open the valve fully by turning the white
protection cap about one turn.
Control the flow temperature via
the heat generator control.
2. Start with a flow temperature between
20°C and 25°C for at least 3 days.
3. Then heat at the maximum design flow
temperature for at least 4 days.

7.4 Cover with thermostat

1. After having completed all building work,
remove the protection cover of the "Unibox
T".
2. Remove the protection cap.
3. Screw the control piston (see illustIllust. 2
on page 21 (8)) onto the valve. Direct the
capillary downwards.
The capillary must not be kinked.
You can hang the cover with the
plastic strip on the venting valve in
order to aid mounting.
4. Fit the valve insulation (see Illust. 2 on page
21(9)) to the "Unibox T".
5. Fit the cover to the "Unibox T".
26
Illust. 10: Fitting of the cover with thermostat
8.
Operation
Set the room temperature at the thermostat.
9.

Maintenance

Regularly check the tightness and function of
the product and its connection points as part of
system maintenance.

10. Removal and disposal

10.1 Disposal

NOTICE
Risk of environmental pollution
Incorrect disposal (for instance with
standard waste) may lead to environ-
mental damage.
f Dispose of packaging material in
an environmentally friendly manner.
f Dispose of the components appro-
priately.
If no return or disposal agreement has been
made, dispose of the product yourself.
f If possible, recycle the components.
f Dispose of components which cannot be
recycled according to local regulations.
Disposal with standard waste is not per-
mitted.
Unibox T
102272280-V01.02.2020

Advertisement

Table of Contents
loading

Table of Contents