INSTALLATION
PROCEDURE
Figure 3-6 – Lining up Instrument
Side and Field Side
Figure 3-7 – Correctly Coupled 356
Connector
3-4
1. Remove and discard the protective covers from both the
instrument side and field side of the connector.
2. Ensure grey profile seal is present on the instrument side of
the connector (see Figure 3-6). If it is missing or damaged,
replace the profile seal before proceeding to step 3.
NOTE
An extra profile seal is shipped with every 356 Instrument
Side Connector. Please contact Rosemount Nuclear for
ordering information if additional profile seals are
required.
3. Line up the groove on the field side with the notch on the
instrument side (see Figure 3-6) and push the two together
firmly.
Field Side
Groove
4. Secure the field and instrument sides together by pushing
the instrument side clamp down over the pegs on the field
side (see Figure 3-7).
Reference Manual
00809-0100-4856 Rev AE
Instrument
Side Notch
Profile Seal
Instrument
Side Clamp
Field Side Peg