Copper Bar Positions (rear view of the cabinet)
(1) Battery Input
(4) Bypass Input
Port Description
Mains input
Bypass input
Battery input
Output
PE
Equipotential ground point Crimped DT terminals
1. Connect the equipotential ground point and the ground bar in the equipment room.
2. Connect the copper bars between the mains input and bypass input (N and PE copper bars).
3. (Perform this step only when the
mains input and bypass input share
a power source) Install the copper
bars (L1, L2, and L3 copper bars)
between the mains input and
bypass input.
(2) UPS Output
(5) Battery PE
Connection Method
Crimped DT terminals
Crimped DT terminals
Crimped DT terminals
Crimped DT terminals
Crimped DT terminals
13
(3) Main Input
(6) Equipotential ground point
Bolt Specifications
M12
M12
M16
M12
M12
M6
Bolt Length Torque
35 mm
47 N· m
35 mm
47 N· m
55 mm
120 N· m
35 mm
47 N· m
35 mm
47 N· m
N/A
4.5 N· m