Operation Instructions; Pre-Startup Checklist; Starting The Ups; Starting The Ups In Normal Mode - Huawei UPS2000 Series User Manual

Hide thumbs Also See for UPS2000 Series:
Table of Contents

Advertisement

UPS2000-G1-(1 kVA–3 kVA)
User Manual

4.1 Pre-Startup Checklist

Table 4-1 describes the items to be checked before you start the UPS.
Table 4-1 Pre-startup checklist
No.
1
2
3
4
5
6
7
8
9

4.2 Starting the UPS

4.2.1 Starting the UPS in Normal Mode

To start the UPS in normal mode, perform the following steps:
Step 1 Switch on the battery breaker.
Step 2 Connect the UPS to the power grid.
Issue 05 (2013-07-17)
Check Item
AC power cable colors comply with electrical regulations.
Cables are securely connected.
Battery cables connect to correct battery terminals in the correct order. The
battery voltage complies with the requirements in appendix A "Technical
Specifications."
Correct labels are attached to power cables.
Cables are neatly routed and securely bound.
Devices are installed and cables are routed in ways that facilitate modification,
capacity expansion, and maintenance.
Ground cables are properly connected.
The voltage between the neutral wire and the ground cable is less than 5 V AC.
Ensure the ground resistance of the UPS shell is less than 0.1ohm.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
4

Operation Instructions

4 Operation Instructions
21

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ups2000-g1 seriesUps2000-g1-1 kvaUps2000-g1-3 kva

Table of Contents