Installing DC Power Feeds for Fan Tray
Figure 15: Power Supply with Lead Wires
1,
3
Caution
Step 6
Use a tie wrap to secure the wires to the rack, so that the wires are not pulled from the terminal block by casual
contact. Make sure the tie wrap allows for some slack in the wire.
Installing DC Power Feeds for Fan Tray
Caution
Cisco ASR 914 Router relies on the protective devices in the building installation to protect against short
circuit, overcurrent, and ground faults. Ensure that the protective devices are properly rated and comply with
national and local codes.
Note
Follow your local practices and requirements when installing power.
Installing the Cisco ASR 914 Router
28
Negative (-) lead wire
2,
4
Do not overtorque the fasteners of the terminal block. The recommended maximum torque is from
25 in.-lb (2.82 N-m).
Positive (+) lead wire
Installing the Cisco ASR 914 Router