Commissioning | Maintenance
ATTENTION!
>
The lifting unit is now operational.
Plug in the unit and carry out a function test. Allow water to flow into the tank. The
>
lifting unit turns on as soon as the electrical power supply is established and the
water level in the tank is above the switch on level.
>
Check all connections/pipe lines for leaks.
>
In addition, observe the specifications in DIN EN 12056-4, DIN EN 12050-3 and
DIN 1986/100.
ATTENTION!
Before carrying out any maintenance work on the unit, all power lines should be
disconnected from the mains and care should be taken that the unit cannot be
inadvertently switched back on. Check the pressure line for damage.
To avoid danger if the power cable is damaged, it must be replaced by the
manufacturer or its service agent or a similarly qualified person.
Change the active charcoal filter:
>
At least once a year.
>
In case of unpleasant odours.
Where water has discharged through the filter.
>
In case of decreasing pump performance remove possible deposits and other
substances from the tank.
In addition, observe the specifications in DIN EN 12056-4, DIN EN 12050-3 and
DIN 1986/100. In case of problems, please contact your CONEL supplier.
11. Commissioning
12. Maintenance
38
Need help?
Do you have a question about the FLOW CUT BOX and is the answer not in the manual?
Questions and answers