SECTION 2 – STARTUP AND OPERATION
• Liquid Line Subcooling = Saturation Temperature
(108.0°F) minus Liquid Line Temperature (95.0°)
= 13.0°F
Subcooling should be 10.0–14.0°F at design conditions.
TABLE 25 - R-410A PRESSURE AND TEMPERA-
TURE CHART
PSIG
TEMP ˚F
0
-60
2
-58
4
-54
6
-50
8
-46
10
-42
12
-39
14
-36
16
-33
18
-30
20
-28
22
-26
24
-24
26
-20
28
-18
30
-16
32
-14
34
-12
36
-10
38
-8
40
-6
42
-4
44
-3
46
-2
48
0
50
1
52
3
54
4
56
6
58
7
60
8
62
10
64
11
66
13
68
14
70
15
72
16
74
17
76
19
40
PSIG
TEMP ˚F
78
20
80
21
85
24
90
26
95
29
100
32
105
34
110
36
115
39
120
41
125
43
130
45
135
47
140
49
145
51
150
53
160
57
170
60
180
64
190
67
200
70
210
73
220
76
225
78
235
80
245
83
255
85
265
88
275
90
285
92
295
95
305
97
325
101
355
108
375
112
405
118
500
134
600
149
700
159
Superheat
Only check superheat after establishing the steady state
operation of the unit, pulling down the discharge air tem-
perature to within the control range, and running the unit
in a fully loaded condition.
The superheat is calculated as the difference between
the actual temperature of the refrigerant gas in the suc-
tion line and the temperature corresponding to the suc-
tion pressure as shown in Table 25.
For example, when the suction pressure is 130 psig and
the suction line temperature is 57.0°F:
• Saturation Temperature for 130 psig = 45.0°F
• Evaporator Superheat = Suction Line Temperature
(57.0°F) minus Saturation Temperature (45.0°F)
= 12.0°F
When adjusting the expansion valve, do not turn the
adjusting screw more than one turn at a time This al-
lows sufficient time (approximately 15 minutes) be-
tween adjustments for the system and the thermal ex-
pansion valve to respond and stabilize.
The superheat setting should be adjusted to 8.0–11.0°F
at design conditions.
Leak Checking
Leak check compressors, fittings, and piping to ensure
there are no leaks. Verify the evaporator distributor
tubes do not have bare copper touching each other or
are against a sheet metal edge. If leak checking a unit
charged with R-410A, ensure the leak test device is ca-
pable of sensing refrigerant R-410A.
Startup (Cooling)
Prestart Checklist
After installation has been completed, make the fol-
lowing checks:
1. Check the electrical supply voltage. Ensure that it
is the same as listed on the unit nameplate.
2. Set the room thermostat to the OFF position.
3. Turn ON the unit electrical power.
4. Set the room thermostat fan switch to ON.
5. Check the indoor blower rotation.
6. Check the blower drive belt tension.
7. Check the unit's supply air (CFM).
FORM 145.32-IOM5