Cisco ONS 15600 Installation Instructions Manual page 10

Install the bay and backplane connections
Hide thumbs Also See for ONS 15600:

Advertisement

NTP- E4 Install the Bay Power and Ground
Before connecting or disconnecting ground or power wires to the chassis, ensure that power is
Warning
removed from the DC circuit. To ensure that all power is OFF, locate the circuit breaker on the panel
board that services the DC circuit, switch the circuit breaker to the OFF position, and tape the switch
handle of the circuit breaker in the OFF position. Statement 140
This equipment must be grounded. Never defeat the ground conductor or operate the equipment in the
Warning
absence of a suitably installed ground conductor. Contact the appropriate electrical inspection
authority or an electrician if you are uncertain that suitable grounding is available. Statement 1024
A readily accessible two-poled disconnect device must be incorporated in the fixed wiring.
Warning
Statement 1022
Warning
Use copper conductors only. Statement 1025
Always use the supplied ESD wristband when working with a powered ONS 15600. Plug the wristband
Caution
cable into either the ESD jack located on the lower-left outside edge of the bay assembly, or the other
ESD jack located at the bottom rear of the shelf.
Complete the
Step 1
Complete the
Step 2
If isolated logic ground is required at this site, complete the
Step 3
task on page
Complete the
Step 4
If the site is in a raised-floor environment with underfloor power, complete the optional
Step 5
and Terminate Raised-Floor Power Cables" task on page
Complete the
Step 6
Complete the
Step 7
Continue with the
Step 8
procedure on page
Stop. You have completed this procedure.
Cisco ONS 15600 Procedure Guide, R7.0
1-10
"DLP-E5 Connect the Office Ground to the ONS 15600" task on page
"DLP-E145 Connect the PDU Ground Cables to the PDU" task on page
17-39.
"DLP-E8 Connect Office Power to the ONS 15600 Bay" task on page
"DLP-E10 Verify Office Power" task on page
"DLP-E171 Verify Fan Operation" task on page
"NTP-E6 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections"
1-11.
Chapter 1
Install the Bay and Backplane Connections
"DLP-E146 Install Isolated Logic Ground"
16-13.
16-15.
17-55.
16-7.
17-37.
16-11.
"DLP-E9 Route