7-2 Adjustment of the position between the needle and the shuttle hook

(1) Turn the power switch OFF.
(2) Turn the sewing machine pulley by
hand then,move up the needle bar①
from the lowest position and stop it at
the position②where the needle bar
timing mark C is matched to the
needle bar bushing bottom line.
NOTE:If the needle class is DP×5,
match the needle bar timing mark D to
the needle bar bushing bottom line②.
(3) Open the cylinder cover②.
(4) Remove the bobbin case③.
(5) Turn the hook retainer lever⑤then,
remove the hook retainer⑥.
(6) Loosen the driver setscrew○ 9 then,
move the driver(No.10)and adjust the
shuttle hook point⑦to be matched
with the center line⑧of the needle.
(7) After the adjustment,tighten the driver setscrew⑨and put the bobbin case④,the hook retainer⑥and
the hook retainer lever⑤back to the original location then close the cylinder cover⑨.
7-3 Adjustment of the clearance between the shuttle hook and the needle
(1) Please take the same procedures as above paragraph 7-2.from(1) to(5).
(2) Loosen the outer hook setscrew③and turn the eccentric pin④so that the clearance between the shuttle
hook point and the needle becomes 0.05~0.1 mm.
(3) After the adjustment,securely tighten the outer hook setscrew③and put the hook retainer and the
bobbin case back to the original location then,close the cylinder cover⑤.