38 kv simple electrical ground & test device (seg&td) lower terminal
Hide thumbs Also See for VCPW-HD:
Table of Contents

Advertisement

38 kV Type VCPW-HD Simple Electrical
Ground & Test Device (SEG&TD) lower
terminal instruction booklet
7 .
Using the racking crank provided, engage the end of the raking
crank with the racking mechanism of the 38 kV SEG&TD (see
Figure 36). Turn the raking crank clock-wise until the SEG&TD
is fully racked into the breaker cell. (Refer to Figure 33 and or
Appendix B for detailed "Step-by-Step Installation Guide" .)
Figure 36. Engagement of the racking crank with the racking
mechanism.
N
otee:
The selector switch handle may appear slightly different ("T" or "L "
shape) however; both operate the same way.
8.
Visually check to make sure the 38 kV SEG&TD is open and
racked into the connected position (see Figure 37).
Figure 37. Visually check that the 38 kV SEG&TD is "Open" and
"Connected" .
9.
Once the 38 kV SEG&TD is fully racked into the connected
position, place key "KC" into Lock #2 and rotate key "KC" to
mechanically unlock the SEG&TD from being closed and to
release key "KB" .
10. Place key "KB" into Lock #1 and rotate it to electrically enable
the 38 kV SEG&TD. This will release Key "KU" and place in
Utility Lock box.
11. Make sure selector switch is in the "OFF" position (see Figure
38). Now rotate Key "KU" to release and store in Utility Box.
Instruction Booklet IB131024EN
Figure 38. Selector switch in the "Off" position.
12. Plug in the remote operator to the receptacle in the front of the
38 kV SEG&TD (see Figure 39).
Figure 39. Remote operator connected to the remote operator
receptacle.
N
otee:
The selector switch handle may appear slightly different ("T" or "L "
shape) however; both operate the same way.
13. Rotate the selector switch to the "Close" position (See
Figure 40).