COMMISSIONING
General commissioning process
Switch on the supply voltage. 15-20 seconds after the self-test, the status LED (LED strip) must
light up blue.
Carry out the prescribed initial testing as per locally applicable guidelines and laws.
Install the casing cover, see section
Installing the connector panel cover
Note
Confirm that a current version of the software is available before you install the connector panel
cover. For further information, see section
Note
The Wallbox must not be used permanently if this cover is absent or damaged. Alternative
covers are not permitted.
26
Installing the casing
cover.
SOFTWARE
Attachment bolts
1. Replace the connector panel cover 1.
2. Attach the connector panel cover again using
the four bolts.
UPDATE.