10.2.2.2 SE71c
Isolate the boiler from the system & drain it down.
Disengage the appliance flue connector from the sump casting. Un-plug the condensate tube from the trap
On the SE71c Model remove the return (lower) connection & heat exchanger connecting pipe from the rear of
the boiler, secured by M8 nuts & washers. Note, there is an 'O' ring used on each fitting.
Support the sump & remove the 4xM6 securing nuts. Lower the sump to expose the heat exchanger & baffles.
To clean the heat exchanger(s), the use of a high pressure water hose (40-80 psi) is recommended with the
resultant discharge being collected in a suitable receptacle.
Primary Exchanger - Insert cleaning nozzle into the burner opening. Switch on the pump & traverse the full
length & circumference of the heat exchanger to remove any deposits
Condensing Heat Exchanger - Using the high pressure hose, traverse the exposed top & side of the heat
exchanger angling the sump to drain.
Should a high pressure hose not be available, the respective heat exchangers will have to be removed from the
casings. Each module holds approximately 4 - 5 litres of water & weighs 50 - 60kg (depending on model). It is
strongly recommended that a minimum of two people are on hand to lift the module from the wall. Alternatively,
two lifting eyes are provided for use with suitable lifting equipment.
Place the module on two blocks of wood so the heat exchanger front casting is supported off the floor to
protect from damage.
Remove the 4xM10 nuts securing the front casting to the aluminium casing & carefully lift the casing vertically
upwards away from the heat exchanger.
Unhook the stainless steel springs & remove the 16 stainless steel baffle plates to expose the finned tubes.
Wire brush both sides of the baffles to remove any deposits.
Thoroughly wire brush the finned tubes.
10.2.3 Re-assembly
Re-assemble in reverse order & refit heat exchanger to the casing using a new gasket. Replace the water
connection gaskets on the rear of the boiler. Re-connect the water connections using new 'O' rings. Carefully
lift the module back onto the wall plate & secure with the M10 nut & bolt on the left hand side mounting. Re-fit
the system pipework & check for soundness.
Re-assemble the fan/transition/burner assembly using new gaskets where necessary, & refit in reverse
order. Test all gas joints broken or disturbed for soundness before firing. Re-light the boiler, check &
adjust the combustion as described in Section 7.
Check thermostat settings & adjust if required.
Re-fit the boiler cover & tidy floor around boiler as necessary.
HAMWORTHY HEATING LTD
31
SHERBORNE
500001167/E

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sherborne se71cSherborne se64he

Table of Contents