STEP 13

INSTALL FRAMES

-Snap in flat fillers, E1-1054, or 2-1/2" long
pieces of E9-1038 at head, jamb, anchor
locations.
-Prior to snapping the assemble frames
together, apply sealant to the interior snap
interface of the mullion, 6" up from the bottom.
-Apply sealant continuously to the front of the
back leg of the sill flashing and immediately set
the frame into the opening.
-Snap assembled frames together if using
screw spline assembly.
See Detail 23.
-Shim jamb and head members with a
minimum of 3/8" shim.
-Anchor the frame to the structure at the sill*,
head, and jamb: 3" from the ends and then
18" to 24" on center.
-Always install a shim at all anchor locations.
Note: Use only flat head fasteners at head
and jamb conditions.
PM-1008-SS
Detail 24
Page-22
YES 45 FS/FI Storefront System
FRAME INSTALLATION
-For end load reactions over 500 lbs.,
attach the sill to the sill flashing using
PM-1008-SS screws.*
-Additionally, add one (1) PM-1008-SS
fastener 2" in both directions from the
centerline of the splice.
See Detail 24.
Anchoring of Sill Member to Sill Flashing
in the state of Florida is to be done per the
detail on the Florida Product Approval:
YES 45 FS - 8731
YES 45 FI - 7019.1
*To determine end load reactions,
consult YKK AP DirecTech or refer
to approved shop drawings
E1-1054 (E9-1038)
Flat Filler - Use At
All Anchor Locations
Sealant
Detail 23
02-4001-09 | Effective Date: May 29, 2018

Hide quick links:

Advertisement

Table of Contents
loading

Related Products for Ykk ap YES 45 FS

This manual is also suitable for:

Yes 45 fi

Table of Contents