1. Concentric terminations must be ordered separately.
SUF 100 120 - 250 models must use the 4 inch concentric
termination; Part Number: 9006328005. Contact your local
distributor or call the parts department phone number on the
back cover of this manual to order concentric terminations.
2. Determine the location for the termination.
note: roof termination is preferred since it is less susceptible
to damage, has reduced chances to intake contaminants and
vent vapors are less visible.
3. When installing a concentric termination vertically through the
roof; ensure that all exterior vertical clearance requirements
for the concentric termination, shown in Figure 30 on page 31
are being maintained. These clearances and those cited by
local and national codes must be maintained.
4. When installing a concentric termination vertically through a
flat roof, the termination's vent cap must be a minimum of 10
feet (3 m) away from any parapet, vertical wall or structure as
shown in Figure 28.
CONCENTRIC TERMINATION(S)
MUST BE A MINIMUM OF 10 FEET
(3 m) AWAY FROM ANY PARAPET,
VERTICAL WALL OR
STRUCTURE.
4 INCH CONCENTRIC TERMINATION
FLAT ROOF CLEARANCE
figure 28
note: if this required 10 foot (3 m) distance to a parapet,
vertical wall or structure cannot be maintained, standard
terminations must be used. See Vertical Termination
Installation on page 27.
5. When installing a concentric termination through a sidewall;
ensure that all exterior sidewall clearance requirements for
the termination, shown in Figure 49 on page 37, are being
maintained. These clearances and those cited by local and
national codes must be maintained.
6. When installing multiple concentric terminations vertically
through a roof or horizontally through a sidewall ensure the
required clearances between terminations and groupings of
multiple terminations are maintained. See pages 32 and 33 for
more information.
7. Cut a 5 inch (13 cm) diameter hole for the 4 inch concentric
termination where the termination will pass through the wall
or roof.
note: Beware of concealed wiring and piping when cutting
through the wall or roof.
8. When installing multiple concentric terminations vertically
through the roof in the same location the termination caps
for all concentric terminations must be at the same height
measured from ground. See multiple Concentric Termination
Arrangements on page 33.
9. Determine if the concentric termination will need to be
shortened
or
lengthened
clearances or to ensure all vent caps are at the same height
when installing multiple terminations vertically through the
roof in the same location.
See Figure 29 on page 31 for the maximum and minimum
lengths allowed for the 4 inch concentric termination.
When extending the length of a concentric termination
do not use couplings. The use of couplings will restrict
flow through the termination and may cause improper
combustion. The termination's intake air and vent pipes must
be replaced with longer sections of the same pipe material
when extending the length of the termination.
Use only SDr-26 pipe to extend the 4 inch concentric
termination.
When shortening the length of the termination carefully
measure and cut the larger (intake air) pipe first. Cut the
same amount of pipe off of the smaller (vent) pipe.
10. Proceed to 4 inch Concentric Termination installation on
page 31.
30
to
accommodate
required

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Suf 60 120Suf 100 150Suf 100 199Suf 100 250

Table of Contents