6. Mounting Instructions (continuation)
•   Lift the REACT2-BATT up to the bracket and insert the heads of two anchor points (present
on the back of the battery unit) into the slots
Risk of injury due to the heavy weight of the equipment.
•   Carefully lift the REACT2-UNO and hook it to the bracket
by inserting the two supports in the slots on the inverter.
Risk of injury due to the heavy weight
of the equipment.
•   Remove the caps from the battery and inverter connectors.
- To remove the battery signal connectors
- To remove the battery power connectors
latch (highlighted in red) and pull it off.
Click
on the bracket
•   Hang up the lower part of the REACT2-BATT to the wall using the
two wall attachment point
•   Hang up the lower part of the REACT2-UNO to the wall using the one anchor point (hole
diameter 11mm).
Click
Click
08
simply pull it.
press the
09
Click
Click
20
.
26
(holes diameter 11 mm).
01
•   Connect the two battery cables between inverter and
Click
battery unit (supplied inside the REACT2-BATT box).
•   Give each cable a pull test to confirm the connection is secure.